Accordingly, the Acceptance Committee has energized the 110KV transformer station on the new Cam Hung – Cam Hoa line (17.2 km long) and other technical equipment.
The Acceptance Council ensures that new equipment and the most related equipment have been checked and accepted and qualified for operation; The protective relay has been set according to the card, connected in the correct phase and phase isotope order, has removed all the mobile ground and is ready to energize.
Mr. Le Hong Phong – Technical Officer of Cam Hoa Solar Power Plant said that after energizing the shock safely, ensuring technical factors, on June 7, it will be energized to the grid and run technically; June 25th will officially generate electricity on the national grid.
After 5 months from the commencement date, the solar power plant project in Cam Hoa commune, Cam Xuyen district, with a capacity of 50 MWp with a total investment of nearly 1,100 billion VND, has been completed on schedule, ensuring technical requirements.
Cam Hoa solar power plant includes 153,000 polycrystalline modules with capacity of 50 MWp; 110KV transformer station; 110KV line from Cam Hoa commune to Cam Hung commune is more than 17 km long to connect to the national electricity system.
The deployment of the solar power project of Hoanh Son Group Joint Stock Company marks the beginning of the development of renewable energy in Ha Tinh.